Information on changes of specification of EDI standards (WIRE Standards) resulting from the implementation of the new cross border scheduling principles
23 April 2010, 00:00
The acceptance tests will be conducted using the test environments of the Scheduling Coordinators and TSO. It is also possible to conduct the acceptance tests of WIRE/UR system by the software vendors. The Scheduling Coordinators who have WIRE/UR systems certified for compliance with the WIRE Standards by software vendors will be exempt from having to hold acceptance tests.
The table below depicts the preliminary time schedule of the implementation project.
The preliminary time schedule of the changes of WIRE Standards | |||
Activity | Responsible | Planned date | |
1 | Update of the Grid Code (IRiESP). | TSO | Immediately after approval of the updated Auction Rules 2010 by 5 TSOs and NRAs. |
2 | Publication of the draft of WIRE Technical Standards 11.0. | TSO | 21.05.2010 |
3 | Consultation of the draft of WIRE Technical Standards 11.0. | Software vendors / Scheduling Coordinators | 07.06.2010 |
4 | Publication of WIRE Technical Standards 11.0. | TSO | 15.06.2010 |
5 | Implementation of the changes resulting from WIRE Technical Standards 11.0 on TSO side. | TSO | do 12.07.2010 |
6 | Testing period of WIRE/UR systems. | Scheduling Coordinators / TSO / Software vendors | od 12.07.2010 do 20.08.2010 |
7 | End of adaptation process of Scheduling Coordinators’ information systems to electronic data exchange according to WIRE Technical Standards 11.0. | Scheduling Coordinators | 31.08.2010 |
The detailed time schedule of the implementation measures related to the changes in WIRE Standards will be described in the Procedure for amending WIRE Standards (Procedura wprowadzania zmian w Standardach technicznych systemu WIRE), which will be published together with new technical Standards of WIRE system 11.0.
The Market Participants who are not equipped with WIRE system should follow the steps set out in the Procedure for connection and acceptance of Scheduling Coordinators’ information systems to the TSO’s information system (Procedura przyłączania i akceptacji systemów informatycznych OR do systemów informatycznych OSP dla WIRE/UR i WIRE).